The
beginnings of the Athens Perimeter Highway were in 1963. The new freeway was one
of the first built outside of Atlanta and was known as GA 350. GA 350 extended
from U.S. 129/GA 15 (present-day GA 15 Alt) east
to U.S. 29/GA 8. The plan was to extend the route west to U.S. 29/78 and east
to a new cloverleaf interchange at Old Hull Road that would later become a new
alignment for U.S. 29, GA 8 and later GA
72. The road to the east was shown as completed as early as 1964, but was
not fully completed until 1967. Click
here to see a more detailed map of GA 350 in 1964. | | Compare
the first appearance of GA 350 in 1963 on the left to the extension to proposed
GA 72 in 1964 on the right. |
In
1966, GA 350 was decommissioned in favor of relocating GA 8 as the state designation
for the entire by-pass. Early 1967 had the entire route complete along the north
side of Athens, making a full by-pass for U.S. 29, despite the fact that U.S.
29 remained along the former route through Athens with GA 8 Business added
in the place of GA 8 with GA 106 on the remainder.
GA 72 was also extended to the freeway portion of GA 8 in 1967, indicating the
future plans to extend GA 72 along another quadrant of the Perimeter that had
still not taken shape. However, part of the route had been completed as early
as 1970 between Milledge Avenue (present GA 15 Alt) and College Station Road,
but was not shown on the GDOT maps in the era. By
1975, more of GA 72 was completed to U.S. 78, but still not shown on the map.
In fact, the proposed GA 72 did not appear on the map until 1977 and only as a
proposed route. By 1980 or 1981, the missing link between U.S. 78 and College
Station Road was completed and GA 72 was designated and fully open to traffic
to Milledge Avenue. This now created a mostly freeway by-pass for most of Athens
with exception to an at-grade intersection with Olympic Drive that remains to
this day. | Note
here that GA 350 is now GA 8. GA 72 is also proposed south of the original GA
350, ending at U.S. 129/441. Parts of the proposed route were already complete,
but did not have full connectivity and were thus not part of GA 72 at the time
(1977 GDOT Map). |
Additional
work on the loop was held off for several more years, and the last section to
be built differed from the rest of the loop in that it would travel in part through
Oconee County. Originally designated as GA 732, work began on the last segment
in the mid-1980's with the new section first appearing on the map in 1984. Work
on the remaining section was completed in 1987. The result was a completed loop
of all different styles and engineering styles due to a project that took nearly
25 years to complete. | | The
map on the left shows the final part of the Athens Perimeter proposed as GA 732,
while the map on the right shows the completed highway divided up among GA 8,
GA 10 and GA 72. Note that several of the highways through Athens, including GA
106 along Old U.S. 129, have been decommissioned compared to the older maps shown.
The remaining black line through Athens is GA 15 Alt. GA 10 Loop would be designated
by 1990 or later (1986 and 1988 GDOT Maps). |
The
completed loop posed a problem: one road with three different route designations.
The east side of the loop was GA 72, south side GA 10 and the north side GA 8.
Even though this was the logical plan, this made the route pretty confusing when
configuring in that every U.S. route passing through Athens followed the loop
as well. Thus, by the early 1990's, the entire loop was redesignated as GA
10 Loop, unifying the route with a single highway number, which was precisely
what the GA 350 designation was supposed to accomplish! When GA 10 Loop
was created, GA 72 was truncated back to where it joins U.S. 29 with GA 8 and
10 also restored through the center of Athens. In
the past few years, the issues of a road that took so long to complete has resulted
in a need to bring greater uniformity to a highway that has such heavy traffic.
Underpasses along the older north end were widened, signs were all upgraded with
new interstate-like exit numbers and numerous safety improvements were made. The
lone at-grade intersection is also planned to be reconstructed into an interchange,
completing limited access along the entire length of the freeway. |